Delivery of Separator for OJSC Syzran Refinery (OJSC OIL COMPANY ROSNEFT) is completed
Delivery of Separator for OJSC Syzran Refinery (OJSC OIL COMPANY ROSNEFT) is completed
Following up the report being released via the web site 21st August 2013 we inform that joint project on delivery of HP Separator (weight 145 tons) with Oktava LLC has been successfully completed.
It is to be recalled that 31st July 2013 Separator was loaded on the section of 12-axle coupling type transporter with its payload of 170 tons (model 14-TO55) in workshop of JSC Uralhimmash and upon covering over 2 000 kilometers of railroads arrived at Syzran Refinery local railway 12th September of the year 2013.
Then the Separator was reloaded on a special trailer by rigging method by means of hydraulic jacks and hydraulic pushers and delivered to the jobsite of Syzran Refinery 24th September 2013.